从上海企事业单位环境信息公开平台获悉,特斯拉上海超级工厂(一期)第二阶段的产线优化项目在 9 月 1 日竣工并开始调试,预计验收期限为 9 月 1 日至 11 月 30 日。据了解,该项目投资总额高达 12 亿元人民币,其中环保投资 8500 万元,占比 7.08%,实际动工时间为去年 12 月 21 日,预计竣工时间为今年 4 月,不过最终延至 9 月才正式竣工。此次的产线优化项目是特斯拉在现有工厂内进行扩建,主要通过提高生产节拍来扩大产能。(贝壳财经)
特斯拉中国再度扩产 上海超级工厂产线优化项目竣工
Source: JIN10 The copyright of this article belongs to the original author/organization.
The views expressed herein are solely those of the author and do not reflect the stance of the platform. The content is intended for investment reference purposes only and shall not be considered as investment advice. Please contact us if you have any questions or suggestions regarding the content services provided by the platform.